4.2. Scheduling to Minimize Lateness: An Exchange Argument

The Problem

  • We have a single resource and a set of n requests to use the resource
  • The resource has a deadline d i and requires a contiguous interval of time t i
  • Each request is flexible: It can be scheduled at any time before its deadline.
  • Each accepted request is assigned an interval of length t i , and different requests are assigned nonoverlapping intervals
  • Let S = the overall start time
  • Each request i is assigned an interval of time of length t i = [ S(i), fi)], where f(i) = S(i)+ t(i)
  • The algorithm must always determine the start time
  • Lateness, l i = f(i) - d(i))
  • l i = 0 if the request i is not late
  • A request is late if it misses the deadline –>f(i)> d i


–> Goal of the algorithm: Minimize the maximum lateness, L = maxi l i by scheduling all requests using nonoverlapping intervals.

Designing the algorithm

  • After quite a bit of analysis, we find that the optimal solution to this problem is using a method called Earliest Deadline First:sort the jobs in increasing order of their deadlines d i and schedule them in this order.
  • Thus jobs are scheduled in the order d 1,d 2,…,d n
courses/cs211/winter2012/journals/jeanpaul/chapterfour_sectionii.1330288566.txt.gz · Last modified: 2012/02/26 20:36 by mugabej
CC Attribution-Noncommercial-Share Alike 4.0 International
Driven by DokuWiki Recent changes RSS feed Valid CSS Valid XHTML 1.0